ConsensusDOCS- are they an improvement over AIA construction contracts?

March 31, 2010

Have you had occasion to use the (relatively) new ConsensusDOCS? Having just completed my manuscript for the North Carolina Construction Law seminar I’m speaking at in May, I’ve been spending a lot of time comparing the American Institute of Architect’s standard contract general conditions, the AIA A201 (2007) to the ConsensusDOCS 200 (2007) and the Engineering Joint Contracts Document Committee (EJCDC) standard general conditions of the contract, C-700 (2007).

I haven’t yet seen litigation over the ConsensusDOCS, so how courts will interpret its provisions remains to be seen. One major difference: the ConsensusDOCS do diminish some of the architect/design professional’s role on the project.

For example, in the change order process, instead of the architect being involved in the contract price and time adjustment (see AIA A201 Section 7.2.1), the ConsensusDOCS 200 calls for the owner and contractor to negotiate in good faith. No mention is made of the design professional’s role. (See 8.1.2).

If you’ve had occasion to work under the ConsensusDOCS, drop me a line and tell me the advantages and disadvantages over other form contracts.

[tweetmeme source= ‘melissabrumback’ single only=false  http://constructionlawnc.com/2010/03/31/consensusdocs-…tion-contracts/ ‎ ]

Advertisements

From → contracts, damages

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: